Question

You have been assigned to automate the core processes of an organization. Due to the size and the complexity of the project you would need multiple teams working concurrently to achieve the project objectives. Which of the following approaches is recommended in this situation?

Options

  1. AgileUP
  2. Scrum of Scrums (SoS)
  3. XP
  4. Scrum

Correct Answer

2

Explanation

Scrum of Scrums (SoS), also known as ?meta Scrum?, is a technique used when two or more Scrum teams consisting of three to nine members each need to coordinate their work instead of one large Scrum team.