Question

A teammate does not finish their work, because they had to help out on another project. Which of the categories of Waste, does this fall into?

Options

  1. Partially done work
  2. Defects
  3. Task Switching
  4. Extra Processes

Correct Answer

3

Explanation

Being assigned to different projects is an example of task switching, which creates waste.