Question

A project team is currently struggling due to frequent interruptions by various delays and impediments. During the sprint retrospective, it was agreed to adopt some form of visual management that can help with work-in-process management and improve the flow. Which of the following tools should be used to facilitate this?

Options

  1. Formal change management process
  2. Ground rules
  3. Kanban board
  4. Silos

Correct Answer

3

Explanation

The team should consider making work visible using Kanban boards and experimenting with limits for the various areas of the work process in order to improve flow. [Agile Practice Guide, 1st edition, Page 32]