Which of the following scheduling techniques is typically used on Agile projects?

Options

  1. Critical chain method
  2. Critical path method
  3. Iterative, on-demand, or pull-based scheduling
  4. Precedence diagraming method

Correct Answer

3

Explanation

Critical path method, critical chain method, and precedence diagramming method are scheduling techniques used in predictive approaches. Agile approaches include iterative scheduling, on-demand scheduling, and pull-based scheduling. [Agile Practice Guide, 1st edition, Page 92]