Question

Which of the following statements regarding Agile planning is incorrect?

Options

  1. Agile plans are changed as new knowledge becomes available.
  2. Agile plans do not cover all of a projects planning at the outset.
  3. Agile planning is spread more or less evenly across the duration of a project.
  4. Agile planning focuses more on change rather than project objectives.

Correct Answer

4

Explanation

Although Agile teams are not only willing but anxious to change, Agile teams do not change plans just for the sake of changing. Agile planning accommodates changes but is still focused on project objectives. [Cohn, M., 2006. Agile Estimating and Planning. 1st ed. Massachusetts: Pearson Education. Page 9]

for more 1500 PMI ACP exam questions.