Question

One of the challenges of planning a release is estimating the velocity of the team. Which of the following is NOT a valid Agile approach to estimate a teams velocity?

Options

  1. Making a forecast.
  2. Using historical values.
  3. Running an iteration.
  4. Conducting a sensitivity analysis.

Correct Answer

4

Explanation

Sensitivity analysis is a risk analysis technique and cannot help in forecasting a teams velocity. The rest of the choices are valid approaches. [Cohn, M., 2006. Agile Estimating and Planning. 1st ed. Massachusetts: Pearson Education. Page 175]