Question

If the amount of new functionality to be developed is fixed, how should a good release plan account for the project uncertainties?

Options

  1. By providing a date range for project completion.
  2. By keeping the project open-ended.
  3. By providing an estimate of standard deviation along with the deadline estimate.
  4. By keeping the completion estimates within the team.

Correct Answer

1

Explanation

If the amount of new functionality is fixed, state your uncertainty as a date range rather than providing a single completion date estimate. The rest of the choices are not recommended Agile practices. [Cohn, M., 2006. Agile Estimating and Planning. 1st ed. Massachusetts: Pearson Education. Page 248]

for more 1500 PMI ACP exam questions.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.